Her kan du finne et utdrag av internasjonale prosjekter som ble fullført med vår støtte. Filtrer referanseprosjektene våre etter dine interesser, etter type struktur, produkter eller prosjektets land.
In southern Staffanstorp, Vikhem, the project Vikhemsporten is under development.
The project consists of five residential buildings with a total of 78 apartments.
The complex includes multi-family residential buildings and residential-service buildings. The high-quality use of the underground structure on difficult building ground requires a reliable waterproofing system.
During the extension of the metro line 2 in Warsaw, a strong ground slab had to be sealed. This lies at a depth of 15 metres below the ground level and about 12 metres below the upper edge of the groundwater table.
In Piraeus, work is being carried out on the extension of metro line 3. MAX FRANK supplies the MAX FRANK Coupler threaded connection for the tunnel section.
A fascinating ensemble of buildings called "Neuer Kanzlerplatz" is currently under construction on the site of the former Bonn Center. The three buildings, one of them a high-rise with a height of 101.5 m and 28 floors, will inspire the future working world with their aesthetics and to serve as a meeting place.
The Varberg tunnel is a strategically important railway project on the West Coast Line, expanding into double tracks and a tunnel which runs beneath the city of Varberg in Sweden.
The GRAND CENTRAL Frankfurt is under construction on a 30,000 sq. m. site adjacent to Frankfurt main railway station. For the floor panels, MAX FRANK supplied Stremaform® formwork elements for working joints with coated metal water stop.
Construction projects with an underground car park require appropriate structural measures to protect the basement, especially in connection with critical groundwater conditions.
Danske Bank’s new headquarters will be located at the old post office property at Bernstorffsgade in Copenhagen and is a central feature in the new district.
In Munich-Ludwigsvorstadt, a real estate project comprising 74 apartments is currently under construction. The residential building is equipped with an underground car park, a supermarket and a pharmacy – all being constructed on the basement and ground floor.
A modern office and commercial building with an underground car park is being built on a site in the port city of Kiel, in the direct vicinity of the Kiel Fjord.
On 8 floors, Sisag AG's new building offers plenty of space for their own employees and, additionally, gives all interested parties public access to a restaurant and hotel with a fantastic mountain panorama.
In spring 2022, a new building for psychiatry will be completed at Norrlands University Hospital in Umeå. For the project, MAX FRANK delivers the sub-structure waterproofing system Zemseal®.
In the harbour of Malmö, the Varvsstaden area has been newly developed for a couple of years now and has become very popular with its close proximity to the water and Malmö city. A preschool, school and sports hall are now under construction.
Great Eastern Quays is a mixed-use masterplan for a 6.2ha site and forms part of the Royal Albert Basin area at the eastern end of the Royal Docks complex.
MAX FRANK supplied Stremaform® permanent formwork for construction joints, assembled on the seabed, for the extension of the "Muelle Poniente Norte" dock in the harbour of Palma de Mallorca.
With the Alnatura working world, an architectural milestone has been reached in terms of sustainability, material efficiency, openness and modern working methods arose.
As part of the “Stuttgart 21” transport infrastructure project, Stuttgart’s existing main railway station is being converted into an underground through-station flooded with light. For the chalice-shaped pillars on the future railway platforms, MAX FRANK is supplying fibre-reinforced concrete single spacers.
A new laboratory building is being built at the TU Chemnitz. The base plate required a targeted introduction of the building loads as well as high tightness against radon.
The treatment plant Waßmannsdorf will be enlarged to catch the rising wastewater volume in the district Dahme-Spreewald. Two additional purification tanks and a mixing water storage will result.
MAX FRANK supplied Shearail® punching shear reinforcement and Stremaform® jointing formwork to Gallions Quarter – a multi-phase development, located in the Royal Albert Basin area of the Royal Albert Docks.
The new August-Kühne-Haus is currently under construction at the historic headquarters of the logistics company Kühne + Nagel in Bremen. MAX FRANK supplied thermally insulating Egcobox® cantilever connectors for the precast sections of the load-bearing exposed concrete façade.
Max Frank Ltd. supplied Pecafil® permanent formwork, plastic side spacers and fibre concrete triangular base spacers to the groundworks of Hilton Garden Inn.
MAX FRANK supplied Stremaform® concrete jointing system to Canary Wharf’s new district. The use of Stremaform® enabled significant time and cost advantages to be achieved on-site.
MAX FRANK Spain supplied fibre concrete spacers for the production of precast concrete parts for the Quito subway tunnel. A total of 30 containers were supplied.
MAX FRANK Tubbox® "blowhole-free" column formers were used for the round columns for the bus station. The Zemdrain® CPF liner, placed inside the Tubbox® column formers, ensures a blowhole-free concrete surface.
The Allmend Tunnel has already been in operation for 46 years and showed various structural damages. With the renovation of the motorway section Thun-Nord - Thun-Süd, the tunnel will also be renovated.
In order to provide thermal insulation in the residential buildings of the settlement Szafarnia in Gdansk, thermal break balcony connectors Egcobox® were used.
Insitex® architectural formliners were chosen for use on an Environment Agency flood prevention scheme in the town of Whitworth in the Rossendale Valley, Lancashire.
Insitu concrete sea walls using NOEplast were selected as an economical and durable solution to the original design of precast units with 'cast in' real-stone cladding.
Situated in the City of London's Square Mile and built around and above Liverpool Street Station, MAX FRANK supplied to the new '5 Broadgate' office estate.
The former New Bridewell Police Headquarters was demolished to make way for 499 beds of purpose built student accommodation and approximately 6,500 sqft of commercial floor space at ground floor level.
Pecavoid® cellular void former was selected as an effective solution to combat slag heave during the construction of a new Anaerobic Digestion (AD) Plant.
MAX FRANK supplied a “self-supporting” concrete jointing system, permanent formwork and sealing solutions to the largest Waste Water Treatment Works in the UK.
The works consisted of the construction of a new spa and hotel extension to the Grade 1 listed historic Rudding Park Hotel nestled within an 18th century Repton landscape.
Tubbox® column formers were used for the round concrete columns at the south-east entrance to the new Breslauer Platz/Hauptbahnhof underground station.
The Vodafone campus includes a 19-story office tower, three building blocks and a parking garage. Bar spacers made of cast concrete were supplied for this purpose.
The CityLife project in Milan is characterized by three towers: "Torre Isozaki", "Torre Hadid" and "Torre Libeskind" - named after the respective architects.
The Egcobox® thermally insulating cantilever connector was used in the creation of a projecting solar protection structure at the State Office of Finance.
The expansion joints were constructed with Stremaform® formwork elements with internal expansion rubber water bar and integrated Egcodorn shear force dowels.
For the thermal decoupling of the balcony slabs, over 1,650 Egcobox® thermally insulating cantilever connectors have been installed in the SKY construction project.
Tubbox® Multi special circular column formers were used in the circular tank of a sewage plant in the municipality of Palazzolo sull'Oglio in northern Italy.
In the bridge structure, the Stabox® special rebar connection for high shear forces were able to guarantee the most demanding requirements for an "indented" working joint.
The coupling of the joints was created by Egcodorn® shear force dowels which were integrated into a formwork element with internal and external rubber water bars.
In the floodplain of Deggendorf, watertight seals of the sophisticated building geometries were created with the Zemseal® sub-structure waterproofing system.
The Egcoscal stair bedding offers high-performance impact sound reduction and greatly improves the comfort of the residents of the Färberstraße Quarter.
The Q 6 Q 7 project gives the city of Mannheim a multifunctional quarter consisting of attractive retail, restaurant and office space, as well as rental apartments.
The Sohlstufe Lehen power station won a category of the "European Concrete Award 2014". MAX FRANK supplied formwork elements and fibre-reinforced concrete distance tubes.
In the Playmobil logistics centre, the transmission of shear forces of slab-form components in the expansion joints is achieved by the use of Egcodubel.
The "Palais an der Oper", the former Residenzpost on Munich's Maximilianstraße, has been renovated and rebuilt as an exclusive residential and commercial building.
The "Ohligsmühle" building complex was built in Wuppertal-Elberfeld. The concrete working joints were securely sealed with Fradiflex® metal water stop.
An office complex with 20,000 sqm of rental space, 47 underground parking spaces and 37 outdoor parking spaces has been built on Nordkanalstraße in Hamburg Hammberbrook.
Nová Karolina is one of the largest urban development projects in the Czech Republic. Modern apartments as well as office and commercial buildings have grown up in Ostrava.
An industrial hall for a German automobile manufacturer is being built near Landshut. This project included the use of the 32 mm diameter Coupler position connection.
The MO.S.E project is a storm surge barrier currently under construction. Installed by the lagoon of Venice it is designed to protect against flooding.
The mine water cleaning plant was the realisation of an environmental protection project for clean water. MAX FRANK supplied sealing technology products.
Approx. 700 Egcotritt light shear force dowels have been installed for sound decoupling between the lift shaft and ceilings in the Eurogate passive house residential complex
In the new elevated tank in Höchsten, Dortmund the service life of the concrete has been provably increased with the water-deflecting Zemdrain® CPF liner.
The internal walls of the water storage tank were lined with the Zemdrain® CPF liner. The use of Zemdrain® increases the service life of the concrete surface.
The Egcovoid® void former was installed in the pension insurance firm's administration building to achieve load activation of the underground car park ceiling.
The Donau City Tower in Vienna is currently the tallest building in Austria. The new landmark with its characteristic "crystal façade" is highly impressive.
For the Clem Jones Tunnel project in Australia, MAX FRANK supplied fibre-reinforced concrete spacers as well as the Intec® injection hose system for joint seal.
CityLife in Milan is to be a new business and residential district. Its landmarks include the three towers Torre Isozaki, Torre Hadid and Torre Libeskind.
The construction of the Citygate project in Vienna began in 2013. It will include a shopping centre with 20,000 sqm of retail space and around 1,000 apartments.
Two new tunnels are being built in the Stuttgart Europaviertel. A mass-spring system with the Egcodorn® DND is being used for the purpose of acoustic decoupling.
The Casa da Música is the municipal concert hall in the Portuguese city of Porto. The concert hall was designed with exposed concrete surfaces inside and out.
The BAYSIDE Hotel opened in 2014 in Scharbeutz on the Baltic Sea coast. The Egcotritt stair landing bearings ensure the soundproofed connection of the balcony slab.
The Stremaform® sound insulation joint was used as a formwork element and provides the necessary sound decoupling between the buildings of the Aubach villas.
A daycare centre for 370 children has been built on the factory site of the "Alte Baumwolle" in Flöha. Saxony's largest daycare centre opened at the end of 2013.